(Photo by Jeff Beach/North Dakota Monitor)
(North Dakota Monitor) – Data center developer Applied Digital is investing $75 million in power system upgrades in eastern North Dakota as it looks to expand into the western part of the state.
Applied Digital will cover the cost of an electrical substation and high-voltage powerline that it needs for the data center it is building near Interstate 29 between Fargo and Harwood.
Minnkota Power Cooperative will own and operate the new facilities. A Minnkota spokesperson said Applied Digital’s covering the upgrades benefits the grid and other customers in the region.
“That infrastructure provides tremendous benefit to the southern Red River Valley,” Ben Fladhammer said.

Traffic Citation Phone Scam Again Circulating in Region
(KNOX) - Local law enforcement is reporting a high rate of a phone scam involving false information about traffic citations. Officials reported late Tuesday afternoon at a number of North Dakota and Minnesota cell customers reported receiving text me...
Apr 07, 2026

University of North Dakota Bookstore Relocates
(Photo by Adam Kurtz/UND Today) (UND Today) - The University of North Dakota Bookstore is preparing to open the doors to its new home, creating an inviting space designed to better serve and connect the UND community. Both the old and the new booksto...
Apr 10, 2026

Mill Road in Grand Forks Closed For The Summer
(File image) (KNOX) - Crews have closed Mill Road at the North Dakota State Mill in Grand Forks. The State Mill will be doing work on their facility this summer with a large crane that will be parked on Mill Road. Local access to businesses along Mil...
Apr 08, 2026

UND Police Officer And Civilian Honored For Life Saving Actions on University Avenue Overpass
(Photo by Adam Kurtz/UND Today) (By Adam Kurtz. UND Today) - A UND police officer and a civilian were honored Thursday, April 2, for their roles in preventing a potential tragedy on a Grand Forks overpass. Cpl. Jose Solis of the UND Police Department...
Apr 09, 2026