Commercial traffic is expected to resume at the Grand Forks Airport today (Friday) with the arrival of a Delta Flight during the ten o’clock hour.
A runway construction project that began August 22nd prevented Delta and Allegiant from landing at the GFK.
The reconstruction of the intersection of two major runways cost around $9.6 million dollars.
GFK Executive Director Ryan Riesinger called it a big project in a short period of time. According to Riesinger crews worked around the clock in 24 hour shifts to be able to get the project accomplished in the quickest period of time…and safely.”
Smaller planes and UND flight students were still able to operate at the airport during the construction.
Investigation into wire fraud at Grand Forks Public Schools continues
(KNOX) - The investigation into the wire fraud at Grand Forks Public Schools remains open and active. In late September, the Mark Sanford Education Center filed a complaint for more than $2.2 million...and said that no data from Grand Forks Public Sc...
Nov 13, 2024
Lane Closure on Gateway Drive in Grand Forks
(KNOX) - East bound traffic on Gateway Drive, Highway 2, in Grand Forks will be down to one lane between N. 20th St. and Columbia Road starting on Tuesday, November 12th. Crews need access to utility lines under the road for private utility work. Th...
Nov 10, 2024
Grand Forks Planning and Zoning Commission Approves Ordinance Change
(KNOX) - The Grand Forks Planning and Zoning Commission approved the removal of the 20% rule in residential districts. Grand Forks City Planner Sierra Johnson says that the change would reduce side yard setback requirements. "This specific ordin...
Nov 11, 2024
Advisory Committee Unveil Recommendations to Address Housing Needs in North Dakota
(North Dakota Monitor) - Gov. Doug Burgum, state legislators and other members of the North Dakota Housing Initiative Advisory Committee released the committee's recommendations for addressing housing needs in North Dakota, with a three-pronged appro...
Nov 12, 2024