(Photo by Jeff Beach/North Dakota Monitor)
(North Dakota Monitor) – The cost of the power line and substation needed by a data center north of Fargo has risen from $75 million to $110 million, but developers say the data center company will still cover the entire cost of the project.
Applied Digital needs the project to power its data center being built between Fargo and Harwood. The data center requires 280 megawatts of power at peak demand.
Applied Digital will pay for the project but it will be owned by Grand Forks based, Minnkota Power Cooperative.
The North Dakota Public Service Commission held a hearing in Fargo on what is known as the Agassiz Transmission Line and Substation.

North Dakota Oil Selling for a Premium
(KNOX) - North Dakota oil shipped on the Dakota Access Pipeline is fetching nearly $7 more per barrel than a U.S. benchmark price amid volatility caused by the Iran war. State regulators aren't sure why prices for North Dakota oil at its destination ...
Apr 22, 2026

East Grand Forks Needs New Parks Director
(KNOX) - East Grand Forks will begin the search for a new Parks & Recreational Director this week. The opening was created by the resignation of Jeremy King. The city council last night (Tuesday) approved advertising the position for the next fou...
Apr 22, 2026

Millions of Americans Could Now Become Canadian Citizens
(KNOX) - Potentially millions of Americans suddenly have a much easier path to Canadian citizenship. A change in the country's laws has prompted a rush of Americans to explore their ancestry and file paperwork seeking dual citizenship. Since the new ...
Apr 24, 2026

Grand Forks Schools Hiring New Assistant Superintendents
(KNOX) - The Grand Forks School Board has approved the hiring of two new assistant superintendents. Chris Triggs will be assistant superintendent of elementary education at a salary of $192,000. Triggs currently oversees the Pingree-Buchanan School ...
18h ago