A spot inspection of the Grand Forks levee system has revealed a crack in a flood wall near the Sorlie Bridge. The crack was discovered by U.S. Army Corp of Engineers this spring.
Without discussion the Grand Forks council last night (Monday) agreed to proceed with repairs to the flood wall at an estimated cost of $100.000 dollars. Bids on the work are due back in late August.
The “fix” is expected to be completed by November 1st.
A more thorough inspection of the 14 miles of levee…two miles of flood wall….and 12 pump stations is expected by the USACE in 2025.


Grain Elevator Fire in Minnesota
(Photo submitted) (KNOX) - Crews battled a large fire at a grain elevator in northwestern Minnesota. Several fire departments responded to the CHS grain elevator in Warren. The Marshall County Sheriff's Office said that Highway 75 was shut down from ...
Apr 01, 2026

Grand Forks Police Respond to Crash
(File image) (KNOX) - Tuesday afternoon officers from the Grand Forks Police Department were dispatched to the intersection of 32nd Avenue South and South 31st Street for the report of a three vehicle accident involving injuries. An investigation rev...
Apr 01, 2026

North Dakota National Guard Being Sent to D.C.
(Photo courtesy of North Dakota National Guard. via the North Dakota Monitor) (North Dakota Monitor) - North Dakota will send 60 National Guard members to Washington, D.C., starting in April, for an estimated three months to help police the city. The...
Mar 30, 2026

Crash in Grand Forks
(File image) (KNOX) - Monday afternoon officers from the Grand Forks Police Department were dispatched to 17th Avenue South for the report of a two vehicle crash, involving one vehicle that had overturned onto its roof. An investigation revealed that...
Mar 31, 2026